Risk register

Potentially dangerous operations on a running Kolla-Ansible 2024.1 platform: their impact and the precautions to take before running them. Ratings are relative to a production cloud with running VMs. The risk IDs are those of the earlier studies; each entry says whether the risk still applies to 2024.1, with the code that shows it. R26 to R30 are new in this study.

Note

Key answers

  • 30 risks (R1–R30), each with what actually happens, its blast radius, VM and API impact, likelihood, severity, precautions and evidence (Matrix).
  • Rated Critical: R7 (openvswitch_vswitchd restart or recreate), R12 (changing the image tag and running deploy instead of upgrade), R14 (bootstrap-servers re-run on a live host), R15 (kolla-ansible stop) and R16 (kolla-ansible destroy). None of the new risks is rated Critical.
  • Computes and VMs: R1. Any config change touching nova-compute, followed by a deploy/reconfigure with a nova tag or no tag, restarts nova_compute, nova_libvirt and nova_ssh on every affected compute, all at once with the default serial 0; whether live migrations in flight fail and whether running VMs keep running are NOT AVAILABLE.
  • Network data plane: R6 (with enable_neutron_agent_ha: yes, the L3 agent wrapper runs neutron-netns-cleanup --force --agent-type l3 before the agent starts) and R7; whether VM traffic is interrupted is NOT AVAILABLE.
  • New in 2024.1: the first 2024.1 check restarts containers whose systemd unit 2023.1 wrote (R26, F16); quorum queues are on by default (R27, F17); upgrade refuses a RabbitMQ minor version skip (R28); genconfig writes HAProxy frontends that no later tagged run applies (R29); the Octavia jobboard needs Redis (R30).
  • Changed in 2024.1: fewer roles read the memcached list (R4, 28 instead of 34); upgrade now runs the RabbitMQ version check (R10); bootstrap-servers installs the engine named by kolla_container_engine (R14); destroy keeps the inventory paths under /etc/kolla and disables the units (R16); prune-images has a Podman branch (R17). R24 still does not hold as written and R25 still does not apply.
  • Likelihood × severity at a glance: the heat map.
  • Likelihood = how likely the operation is to cause the impact when the triggering condition is present.
  • Severity = worst realistic outcome.
  • Evidence cites the 2024.1 source lines, or the study section that cites them. Nothing was run. NOT AVAILABLE marks outcomes that the sources do not establish.

Matrix

# Risk Likelihood Severity
R1 Config change touching nova-compute High High
R2 Enabling or disabling a service with a logrotate or fluentd entry High Medium–High
R3 Changing RabbitMQ membership, password or port Certain High
R4 Changing memcached membership Certain High
R5 ml2_conf.ini override meant for neutron-server Certain (neutron-server hosts only) Medium (High where agents share the neutron-server host)
R6 neutron_l3_agent restart with enable_neutron_agent_ha: yes Certain (if HA flag) High
R7 openvswitch_vswitchd restart or recreate Certain on image change Critical
R8 HAProxy config change Certain if changed High
R9 MariaDB config change or image change Certain if changed High
R10 RabbitMQ image change (upgrade) Certain on upgrade Medium–High
R11 kolla-ansible pull – Low (bandwidth)
R12 Image tag change run with deploy instead of upgrade Certain Critical
R13 Rebuilt image under the same tag, then deploy/reconfigure without pull – Medium (drift)
R14 bootstrap-servers re-run on a live host Medium Critical
R15 kolla-ansible stop Certain Critical
R16 kolla-ansible destroy Certain Critical
R17 prune-images Low Low
R18 mariadb_recovery Certain High
R19 Keystone reconfigure Certain if changed Medium–High
R20 Glance reconfigure / deploy Certain Medium
R21 Enabling Swift (or another Glance backend) on a running cloud High High
R22 Inventory reordering Medium High
R23 Any run with --limit on a large inventory Certain Low (time), Medium (drift)
R24 Effective container stop timeout is 10 s (60 s since 2023.1) Certain Medium
R25 -t common believed to reconfigure fluentd/cron Does not apply in 2024.1 –
R26 First 2024.1 deploy/reconfigure on containers whose unit 2023.1 wrote (new) Certain (such containers) High
R27 Quorum-queue default on a cloud with classic queues (new) Certain (default kept) High
R28 upgrade with RabbitMQ more than one minor version behind (new) Certain on the 2023.1 default image; otherwise NOT AVAILABLE High
R29 HAProxy frontend change written by genconfig (new) High (with genconfig) Medium (drift)
R30 Octavia with the amphora provider and no Redis (new) Certain (default) Medium

R1 — Config change touching nova-compute

Still applies to 2024.1 CODE.

Operation / trigger Any config change touching nova-compute (override, global flag, password, RabbitMQ list, the 2024.1 quorum-queue default of R27) followed by deploy/reconfigure with a nova tag or no tag
What actually happens nova_compute and nova_libvirt and nova_ssh restart on every affected compute, all at once (serial 0). The cause is the loop-notify behaviour: Check nova-cell containers loops over nova_cell_services with notify: "Restart {{ item.key }} container", and ansible-core 2.16.20 processes every executed item's _ansible_notify when the loop as a whole is changed. nova_libvirt is a container only when enable_nova_libvirt_container is true, which is the default for nova_compute_virt_type kvm/qemu; with a host libvirt (other virt types) there is no nova_libvirt restart
Blast radius all computes
VM impact libvirtd restart (container nova_libvirt, retried up to 5 times: "when guests running, nova_libvirt will raise error even though it is removed"); NOT AVAILABLE whether live migrations in flight fail and whether running VMs keep running
API impact nova-compute restarts on each host; NOT AVAILABLE how long it is down
Likelihood High
Severity High
Precautions genconfig + diff, then deploy-containers --limit in batches, or ANSIBLE_SERIAL (honoured by reconfigure and upgrade) / -e kolla_serial=<n>; drain live migrations first; validate libvirt restart behaviour in staging
Evidence roles/nova-cell/tasks/check-containers.yml:2-22, roles/nova-cell/defaults/main.yml:2-64, roles/nova-cell/handlers/main.yml:74-117,151-168 (retries at :110-113), group_vars/all.yml:827,1127, nova.yml:125-147 (serial: '{{ kolla_serial|default("0") }}' at :140), tools/kolla-ansible:490-493,522,531; ansible-core 2.16.20 lib/ansible/executor/playbook_executor.py:300-302 (serial 0 = one batch), lib/ansible/executor/task_executor.py:126-130 and lib/ansible/plugins/strategy/__init__.py:648-673 (one changed item marks the loop changed, then every item's _ansible_notify is processed); Tags §2.4; Nova deep dive §5

R2 — Enabling or disabling a service with a logrotate or fluentd entry

Still applies to 2024.1 CODE, with the reach it has had since 2023.1: common is its own play, tagged common only, on the cron, fluentd, kolla-logs and kolla-toolbox groups. The lists changed (removed services gone, redis logrotate entry added) and the common config step now makes sure the fluentd image is present.

Operation / trigger Enabling or disabling a service that has a fluentd input entry (fluentd_input_openstack_services, e.g. barbican) or a logrotate entry (enable_X for most services) in globals.yml, then running the common play (an untagged run, or -t common)
What actually happens td-agent.conf (its 00-global input lists the enabled OpenStack services) and logrotate.conf render differently on every host of the common play → Restart fluentd container / Restart cron container; then Check common containers (compare_container runs kolla_set_configs --check in each container) reports changed and loop-notify also notifies kolla_toolbox. With the multinode inventory these are the control, network, compute, storage and monitoring hosts. A tagged service run (-t nova) does not run the common play: the files keep the old content until a later untagged or -t common run. Nova/Cinder/Glance configs gain sections (e.g. [barbican]) → those services restart when their play runs. Flags in neither list (e.g. enable_ovn, enable_memcached) leave both files unchanged; in 2024.1 enable_redis has a logrotate entry, and enable_prometheus_fluentd_integration, enable_letsencrypt and enable_fluentd_systemd add fluentd inputs. New in 2024.1: before rendering, the play runs ensure_image on the fluentd image (pulled when absent) and reads its labels
Blast radius fleet-wide (untagged run or -t common); none for fluentd/cron on a tagged service run
VM impact fluentd, cron and kolla_toolbox are none of the containers that Tags §3.1 traces to running VMs CODE; NOT AVAILABLE whether their restart affects VMs another way (Apply common changes (fluentd, cron, kolla_toolbox) §3); Nova restarts as R1
API impact the services whose configs changed restart (stop with the docker_graceful_timeout of 60 s, then start; R24); NOT AVAILABLE how long their APIs are unavailable, and whether the fluentd, cron and kolla_toolbox restarts affect APIs
Likelihood High
Severity Medium–High
Precautions Treat enable_* changes as fleet-wide changes. Roll out with --limit batches; apply the common side deliberately with -t common; make sure the fluentd image is in the registry before a -t common run or genconfig
Evidence site.yml:88-103 (Apply role common, hosts cron/fluentd/kolla-logs/kolla-toolbox, tags: common); inventory/multinode:49-54,203-213; roles/common/tasks/config.yml:42-91 (fluentd image and labels), :140-203 (td-agent.conf), :205-270 (logrotate.conf), roles/common/defaults/main.yml:154-210 (fluentd service list), roles/common/tasks/check-containers.yml:2-17, roles/common/tasks/deploy.yml:1-9; module_utils/kolla_container_worker.py:20, :58-65, module_utils/kolla_docker_worker.py:146-181 (config check); loop-notify (Tags §2.4); roles/nova-cell/templates/nova.conf.j2:259-264, nova.yml:125-147

R3 — Changing RabbitMQ membership, password or port

Still applies to 2024.1 CODE.

Operation / trigger Changing RabbitMQ group membership (adding/removing a controller), RabbitMQ password or port
What actually happens rpc_transport_url and notify_transport_url (one entry per host of the rabbitmq group, with user, password and port) change in every messaging service on every host → all nova, neutron (and any compute-side agent) containers restart; Update cell rewrites the cell's MQ URL when it differs
Blast radius all hosts
VM impact as R1 plus neutron agent restart; NOT AVAILABLE its effect on flows
API impact yes
Likelihood Certain
Severity High
Precautions Plan as a maintenance; batch with --limit; verify RabbitMQ cluster health first
Evidence group_vars/all.yml:241-258; roles/nova-cell/tasks/create_cells.yml:31-55; loop-notify (Tags §2.4)

R4 — Changing memcached membership

Still applies to 2024.1 CODE; 27 roles loop over the list instead of 33 (freezer, murano, sahara, senlin, solum and vitrage are gone); a 28th, telegraf, names the group only to test whether its own host runs memcached (roles/telegraf/templates/telegraf.conf.j2:54-57).

Operation / trigger Changing memcached membership
What actually happens 27 roles loop over groups['memcached'] in their templates (grep of groups['memcached'] in roles/*/templates and roles/*/defaults gives 28 roles, telegraf only testing its own host: aodh, barbican, blazar, ceilometer, cinder, cloudkitty, cyborg, designate, glance, gnocchi, heat, horizon, ironic, keystone, magnum, manila, masakari, mistral, neutron, nova, octavia, placement, swift, tacker, telegraf, venus, watcher, zun), so their services restart when their plays run; NOT AVAILABLE whether cached tokens are lost. Not only the control plane: neutron.conf is rendered for every neutron agent, so neutron_openvswitch_agent restarts on every compute and network node, and the dhcp, l3 and metadata agents, which get the same file, restart on network nodes; cinder.conf reaches every cinder service (cinder-volume/backup included) and ceilometer.conf every ceilometer service (ceilometer-compute included). Compute nova.conf (nova-cell) has no memcached list
Blast radius controllers + network nodes + all computes (+ storage)
VM impact OVS agent restart; NOT AVAILABLE its effect on flows, and whether router/DHCP traffic is interrupted on network nodes; with enable_neutron_agent_ha, the R6 netns cleanup
API impact memcached server list changes; NOT AVAILABLE effect on auth latency and Horizon sessions
Likelihood Certain
Severity High
Precautions Plan as a dataplane change, like R3: batch with --limit or ANSIBLE_SERIAL, network nodes one at a time; low-traffic window
Evidence fact sheet B §3.9 item 2, §3.10; Memcached; roles/neutron/templates/neutron.conf.j2:123, roles/neutron/tasks/config.yml:87-122; roles/cinder/tasks/config.yml:75-93, roles/cinder/templates/cinder.conf.j2:146; roles/ceilometer/tasks/config.yml:196-214, roles/ceilometer/templates/ceilometer.conf.j2:69

R5 — ml2_conf.ini override meant for neutron-server

Still applies to 2024.1, as narrowed in 2023.1 CODE: ml2_conf.ini is rendered only for neutron-server and neutron-infoblox-ipam-agent; openvswitch_agent.ini has its own template and its own override files, so an ml2_conf.ini override does not reach the OVS agents (F11).

Operation / trigger /etc/kolla/config/neutron/ml2_conf.ini override (meant for neutron-server)
What actually happens neutron_server (and neutron_infoblox_ipam_agent if enabled) restarts. On a host that also runs neutron agents (e.g. control and network roles on the same host), loop-notify in Check neutron containers also restarts every neutron container of that host, the OVS, dhcp, l3 and metadata agents included. OVS agents on hosts without neutron-server are not touched by this override. The OVS agent override is neutron/openvswitch_agent.ini
Blast radius neutron-server hosts (and the agents that share them)
VM impact none on hosts without neutron-server; where agents share the host: OVS agent restart, NOT AVAILABLE its effect on flows, and whether router/DHCP traffic is interrupted
API impact neutron-server restart
Likelihood Certain (neutron-server hosts only)
Severity Medium (High where agents share the neutron-server host)
Precautions Put server-only options in neutron/neutron-server.conf or neutron/ml2_conf.ini; agent options in neutron/openvswitch_agent.ini; check the rendered diff
Evidence roles/neutron/tasks/config.yml:159-179 (services_need_ml2_conf_ini), :198-213 (openvswitch_agent.ini), roles/neutron/tasks/check-containers.yml:2-19 (loop-notify, Tags §2.4)

R6 — neutron_l3_agent restart with enable_neutron_agent_ha: yes

Still applies to 2024.1 CODE; neutron_l3_agent_failover_delay (default 0) can stagger the restarts, and the cleanup also reads fwaas_driver.ini when FWaaS is enabled (F12).

Operation / trigger Any restart of neutron_l3_agent with enable_neutron_agent_ha: yes (default no)
What actually happens the wrapper runs neutron-netns-cleanup --force --agent-type l3 before the agent starts (the wrapper's comment: "Remove all l3 related netns in case of multiple active routers in l3 high available mode"), then neutron-l3-agent starts CODE. The handler first starts stopped agents, then restarts running agents in a loop over the hosts of neutron_l3_agent_running_True, pausing neutron_l3_agent_failover_delay seconds between items (default 0: no spacing) CODE. NOT AVAILABLE What the command deletes: it is neutron code, which is not in these sources (F12)
Blast radius network nodes (and computes with enable_neutron_dvr)
VM impact NOT AVAILABLE whether north-south and floating-IP traffic of the routers on that node stops, whether and when neutron-l3-agent rebuilds the namespaces, and whether HA routers fail over
API impact none
Likelihood Certain (if HA flag)
Severity High
Precautions Restart network nodes one at a time; fail routers over first; set neutron_l3_agent_failover_delay to space the restarts
Evidence roles/neutron/templates/neutron-l3-agent-wrapper.sh.j2:5-20; group_vars/all.yml:813,816; roles/neutron/handlers/main.yml:90-157, roles/neutron/defaults/main.yml:78-92, :649-651

R7 — openvswitch_vswitchd restart or recreate

Still applies to 2024.1 CODE. New in the 2024.1 image: openvswitch_db converts conf.db at start when ovsdb-tool needs-conversion says so.

Operation / trigger openvswitch_vswitchd restart or recreate (image change, start-ovs change, -t openvswitch with a changed image, the first 2024.1 check of a container whose unit 2023.1 wrote (R26); also any openvswitch_db-only drift, e.g. a start-ovsdb-server change or a db image, volume or dimension change: check-containers loops over both OVS services, so loop-notify (Tags §2.4) also notifies the vswitchd handler, which runs after the db restart and wait)
What actually happens ovs-vswitchd (the userspace daemon) restarts. The image only runs modprobe openvswitch (the kernel module is loaded, never unloaded or reloaded), and start-ovs launches ovs-vswitchd with no flow save/restore. Bridges and ports persist in conf.db on the openvswitch_db volume; the db image creates conf.db if absent and runs ovsdb-tool convert when a conversion is needed. NOT AVAILABLE Whether the OpenFlow tables held by the old daemon are lost, and whether neutron-openvswitch-agent (or ovn-controller with OVN) reprograms them
Blast radius per host (all OVS hosts at once with serial 0)
VM impact NOT AVAILABLE whether all VM network traffic on the host is interrupted until flows are restored, and for how long
API impact none
Likelihood Certain on image change
Severity Critical
Precautions Upgrade or recreate OVS host by host with evacuation or acceptance; never fleet-wide with serial 0
Evidence roles/openvswitch/handlers/main.yml:2-44, roles/openvswitch/tasks/check-containers.yml:2-18, roles/openvswitch/templates/start-ovs.j2:2, roles/openvswitch/defaults/main.yml:86; kolla docker/openvswitch/openvswitch-vswitchd/extend_start.sh:8, docker/openvswitch/openvswitch-db-server/extend_start.sh:3-10; Open vSwitch; Kolla images §5

R8 — HAProxy config change

Still applies to 2024.1, with the staged restart of 2023.1 CODE: the loadbalancer handlers restart the backups before the node that holds the VIP. New in 2024.1: a Restart haproxy-ssh container handler (Let's Encrypt only) runs last, on every host at once, and the single external frontend (off by default) adds a map file that also notifies the restart.

Operation / trigger HAProxy config change (any service frontend via haproxy-config, the external-frontend-map block, certs, haproxy.cfg); also the first 2024.1 run on a 2023.1 cloud: the haproxy container definition gained a volume, and its unit was written by 2023.1 (R26)
What actually happens haproxy is stopped and started (never reloaded). The handlers first find which host holds kolla_internal_vip_address; every backup host stops and restarts haproxy (all backups at once) and waits for haproxy_monitor_port; then the VIP holder stops haproxy, starts it and waits for the port. On a haproxy-only change keepalived is not stopped, so the VIP stays on a node whose haproxy is down until it is back; keepalived runs a check_alive track script (interval 2, fall 2) by default. Every stop and start handler is skipped under kolla_action config (R29). NOT AVAILABLE whether that script moves the VIP during the master restart, and for how long the APIs are unreachable
Blast radius all APIs + all DB traffic (database_address is kolla_internal_fqdn; enable_proxysql defaults to no)
VM impact none directly; NOT AVAILABLE whether nova/neutron get DB errors while haproxy restarts
API impact yes
Likelihood Certain if changed
Severity High
Precautions ANSIBLE_SERIAL=1 for haproxy changes; --skip-tags haproxy when you don't intend to change frontends
Evidence roles/loadbalancer/handlers/main.yml:1-34 (VIP lookup), :54-68,90-118 (backups), :179-193,224-252 (master), :210-222 (master keepalived stopped only on Restart keepalived container), :331-345 (haproxy-ssh); roles/haproxy-config/tasks/main.yml:2-23, :25-53 (single external frontend); site.yml:105-327; roles/loadbalancer/templates/keepalived/keepalived.conf.j2:1-8, :15, roles/loadbalancer/defaults/main.yml:121 (new haproxy volume), :187; group_vars/all.yml:49,83,839; HAProxy and keepalived; fact sheet A §1.8

R9 — MariaDB config change or image change

Still applies to 2024.1, with the restart mechanism of 2023.1 CODE: the handlers only group hosts; the restart is a separate play with serial: "33%". Every MariaDB play now sets max_fail_percentage, default 100, which stops nothing early.

Operation / trigger MariaDB config change or image change
What actually happens restart mariadb puts running nodes in group mariadb_restart and new nodes in mariadb_start. The Restart mariadb services play then restarts them in batches of int(33% × hosts) or at least 1 (one node at a time for 3 nodes); each node waits up to 10 × 6 s for its port and for WSREP Synced. If every host of a batch fails, ansible-core stops the playbook, so later batches are not restarted. HAProxy's single active backend is the first host of the default shard (the others are backup). NOT AVAILABLE In which order group_by places the hosts, hence whether the active backend restarts first
Blast radius DB cluster
VM impact none directly
API impact DB connection resets
Likelihood Certain if changed
Severity High
Precautions Check wsrep_cluster_size and Synced on all nodes before; take a backup (mariadb_backup); watch between batches
Evidence roles/mariadb/handlers/main.yml:56-73, mariadb.yml:18-52, roles/mariadb/tasks/restart_services.yml:2-51, roles/mariadb/defaults/main.yml:64, group_vars/all.yml:477; ansible-core 2.16.20 lib/ansible/utils/helpers.py:25-34 (percentage → int(...) or 1), lib/ansible/executor/playbook_executor.py:207-209, :219-220 (a fully failed batch ends the playbook); MariaDB; fact sheet B §1.2, §1.5, §1.8

R10 — RabbitMQ image change (upgrade)

Still applies to 2024.1, with the rolling restart of 2023.1 CODE: upgrade does not stop all brokers; it restarts them in serial: "33%" batches, draining each one first. Changed in 2024.1: upgrade now runs the RabbitMQ version check first (R28).

Operation / trigger RabbitMQ image change (upgrade), or kolla-ansible rabbitmq-upgrade <version>
What actually happens upgrade.yml runs version-check, then (without om_enable_rabbitmq_high_availability, the default) removes the ha-all policy, then config, feature-flags and check-containers; the restart handler only adds the host to rabbitmq_restart. The Restart rabbitmq services play then, per batch of int(33% × hosts) or at least 1, puts the node into maintenance mode (rabbitmq_upgrade drain), recreates the container and waits with rabbitmqctl wait --timeout 60. rabbitmq-upgrade runs the same plays with the image rabbitmq-<version>. NOT AVAILABLE whether clients reconnect without errors while a broker is drained
Blast radius all RPC
VM impact NOT AVAILABLE whether nova-compute heartbeats are lost and services are reported down
API impact NOT AVAILABLE whether API calls fail while a broker restarts
Likelihood Certain on upgrade
Severity Medium–High
Precautions Maintenance window; watch for agent and compute services reported down; check the running RabbitMQ version first (R28)
Evidence roles/rabbitmq/tasks/upgrade.yml:1-12, roles/rabbitmq/tasks/remove-ha-all-policy.yml:2-29, roles/rabbitmq/handlers/main.yml:2-6, rabbitmq.yml:30-49, roles/rabbitmq/tasks/restart_services.yml:2-39, rabbitmq-upgrade.yml:18-21, tools/kolla-ansible:585-590; RabbitMQ; fact sheet B §2.8

R11 — kolla-ansible pull

Still applies to 2024.1 CODE; the pull goes to Docker or Podman per kolla_container_engine.

Operation / trigger kolla-ansible pull
What actually happens downloads images on every host: one pull_image per enabled container mapped to the host (retried service_images_pull_retries times, default 3)
Blast radius registry + network
VM impact none
API impact none
Likelihood –
Severity Low (bandwidth)
Precautions Run ahead of maintenance; rate-limit with --forks; local registry mirror
Evidence roles/service-images-pull/tasks/main.yml:2-18, roles/service-images-pull/defaults/main.yml:6; module_utils/kolla_docker_worker.py:189-223; module_utils/kolla_podman_worker.py:455-474; library/kolla_container.py:410-420 (engine dispatch)

R12 — Image tag change run with deploy instead of upgrade

Still applies to 2024.1 CODE.

Operation / trigger Changing openstack_tag / *_tag and running deploy instead of upgrade
What actually happens every container is recreated (fleet-wide); upgrade-specific steps (the nova-status upgrade check, the Nova reload plays, online migrations except Placement's, which run inside bootstrap_placement, and, with the non-default ironic_enable_rolling_upgrade: no, Ironic's inside bootstrap_ironic) do not run. Neutron: instead of the rolling expand → restart → contract (default neutron_enable_rolling_upgrade: yes), bootstrap_neutron runs neutron-db-manage … upgrade head for neutron and for each enabled subproject (neutron-fwaas, networking-sfc, neutron-dynamic-routing, neutron-vpnaas, vmware-nsx, tap-as-a-service) with the new image before the handlers restart the old neutron_server containers; NOT AVAILABLE whether upgrade head applies the expand and contract branches together, which would run contract migrations under live old-version servers
Blast radius fleet-wide
VM impact as R1 + R7 + R8 together
API impact yes
Likelihood Certain
Severity Critical
Precautions Use pull then upgrade (2024.1 docs, which also recommend prechecks before it); per-service tags; ANSIBLE_SERIAL
Evidence module_utils/kolla_container_worker.py:67-89, module_utils/kolla_docker_worker.py:107-122, :341-363 (new image → recreate); doc/source/user/operating-kolla.rst:164-199; nova.yml:180-302 (reload and online-migration plays, kolla_action == 'upgrade' only), roles/nova/tasks/upgrade.yml:9-39; roles/neutron/tasks/deploy.yml:20-23, roles/neutron/tasks/bootstrap_service.yml:2-21, roles/neutron/defaults/main.yml:674-687, :727-733, roles/neutron/tasks/upgrade.yml:4-8, roles/neutron/tasks/rolling_upgrade.yml:13-89; kolla docker/neutron/neutron-server/extend_start.sh:5-13, docker/placement/placement-api/extend_start.sh:5-9, docker/ironic/ironic-api/extend_start.sh:5-8; roles/ironic/tasks/bootstrap_service.yml:16, roles/ironic/defaults/main.yml:310; Kolla images §4; F15

R13 — Rebuilt image under the same tag, then deploy/reconfigure without pull

Still applies to 2024.1 CODE, with Docker and with Podman (F4).

Operation / trigger Rebuilt image pushed under the same tag, then deploy/reconfigure without pull
What actually happens nothing changes (only absent images are pulled; the comparison uses the local image of that tag). After pull: recreate, plus loop-notify restarts
Blast radius – / role-wide
VM impact as R1
API impact –
Likelihood –
Severity Medium (drift)
Precautions Use immutable tags; always pull deliberately
Evidence module_utils/kolla_docker_worker.py:71-79 (local image lookup), :107-122 (image id compare), :341-372 (pull only if absent); module_utils/kolla_podman_worker.py:257-271, :507-527; loop-notify (Tags §2.4)

R14 — bootstrap-servers re-run on a live host

Still applies to 2024.1 CODE; the work comes from ansible-collection-kolla (openstack.kolla.baremetal). New in 2024.1, the engine role and its SDK role follow kolla_container_engine (docker by default, or podman).

Operation / trigger bootstrap-servers re-run on a live host
What actually happens with Docker, can restart the Docker daemon (if daemon.json or the Docker unit changes; docker_systemd_reload: false by default, so the handler restarts rather than reloads) → NOT AVAILABLE whether every container on the host stops and how the kolla-<name>-container.service units (which declare After=/Wants=docker.service) bring them back; all hosts at once by default. Also disables firewalld/ufw (disable_firewall: True), sets SELinux permissive, and removes host packages: on Debian lxd, lxc, open-iscsi and, with the libvirt container, libvirt-bin; on RedHat, with the libvirt container, libvirt, libvirt-daemon, iscsi-initiator-utils
Blast radius per host / fleet
VM impact a Docker restart affects nova_libvirt and OVS → see R1/R7
API impact yes
Likelihood Medium
Severity Critical
Precautions Run only with --limit on new hosts, or -e kolla_serial=1; diff daemon.json first
Evidence kolla-host.yml:4-14; tools/kolla-ansible:485-489; ansible-collection-kolla roles/baremetal/tasks/main.yml:2-9, roles/baremetal/tasks/install.yml:3-38, roles/baremetal/tasks/post-install.yml:2-28, roles/baremetal/defaults/main.yml:25-37, roles/packages/tasks/main.yml:15-23, roles/packages/defaults/main.yml:25-34, roles/docker/tasks/config.yml:9-53, roles/docker/handlers/main.yml:2-15, roles/docker/defaults/main.yml:65; module_utils/kolla_systemd_worker.py:20-39, :50-54; fact sheet E §1–2

R15 — kolla-ansible stop

Still applies to 2024.1 CODE.

Operation / trigger kolla-ansible stop --yes-i-really-really-mean-it
What actually happens stops all Kolla containers (incl. nova_libvirt, OVS, MariaDB) on targeted hosts, except those named in skip_stop_containers; each stop goes through the container's systemd unit when it exists
Blast radius targeted hosts
VM impact nova_libvirt and OVS containers stopped; NOT AVAILABLE whether VM network traffic stops (see R7)
API impact yes
Likelihood Certain
Severity Critical
Precautions Use --limit + tags + skip_stop_containers; MariaDB then needs mariadb_recovery
Evidence tools/kolla-ansible:533-545; roles/service-stop/tasks/main.yml:2-12; module_utils/kolla_docker_worker.py:415-431; Stop and destroy; fact sheet B §1.3 (stop), §1.8 item 4

R16 — kolla-ansible destroy

Still applies to 2024.1 CODE. Changed in 2024.1: the inventory paths passed to the command are kept under /etc/kolla, and the container units are disabled before they are stopped.

Operation / trigger kolla-ansible destroy --yes-i-really-really-mean-it
What actually happens disables, stops and removes containers and their kolla-*-container.service units, volumes, /etc/kolla/* (except passwords.yml, globals.yml, globals.d, kolla-build.conf, config, certificates and the inventories passed with -i), all network namespaces and tap/brq/vxlan links (tools/cleanup-host). tools/cleanup-containers stops before anything when qemu processes run next to nova_libvirt
Blast radius targeted hosts incl. deploy host (hosts: all)
VM impact total
API impact total
Likelihood Certain
Severity Critical
Precautions Never on production; there is no --limit safety net beyond what you pass
Evidence destroy.yml:2-9; tools/kolla-ansible:458-484; roles/destroy/tasks/cleanup_containers.yml:2-3, roles/destroy/tasks/cleanup_host.yml:2-17; tools/cleanup-containers:16-22, :43-67, tools/cleanup-host:5-23, :71-103; Stop and destroy; fact sheet E §6

R17 — prune-images

Still applies to 2024.1 CODE; new Podman branch.

Operation / trigger prune-images --yes-i-really-really-mean-it
What actually happens with Docker, runs docker_prune with images: yes and the filter label: kolla_version on the baremetal hosts; with Podman, podman image prune --force --filter 'label=kolla_version'. NOT AVAILABLE Whether only dangling images are removed: that is the behaviour of the docker_prune module (community.docker) and of Podman, neither of which is in these sources
Blast radius per host
VM impact none
API impact none
Likelihood Low
Severity Low
Precautions –
Evidence tools/kolla-ansible:565-576; prune-images.yml:4-13; roles/prune-images/tasks/prune_images.yml:2-16; fact sheet E §7

R18 — mariadb_recovery

Still applies to 2024.1 CODE.

Operation / trigger mariadb_recovery
What actually happens unless mariadb_recover_inventory_name is given, stops every MariaDB node, even healthy ones, runs a wsrep recovery container on each, and bootstraps from the host with the highest seqno
Blast radius DB cluster
VM impact none directly
API impact full DB outage
Likelihood Certain
Severity High
Precautions Only when the cluster is fully down; identify the node with the highest seqno manually first
Evidence mariadb_recovery.yml:2-13; roles/mariadb/tasks/recover_cluster.yml:18-96, :98-100; Database operations; fact sheet B §1.3 (Recovery), §1.8 item 5

R19 — Keystone reconfigure

Still applies to 2024.1 CODE.

Operation / trigger Keystone reconfigure (any keystone change, including memcached/RabbitMQ membership)
What actually happens all keystone containers restart on all hosts at once (serial 0); fernet keys are pushed with rsync --delete from the first host where keystone_fernet runs (else the first keystone host), deleting others' keys; the bootstrap container (db sync) runs once
Blast radius identity
VM impact none
API impact NOT AVAILABLE whether authentication fails while keystone restarts
Likelihood Certain if changed
Severity Medium–High
Precautions ANSIBLE_SERIAL; verify fernet key consistency before and after
Evidence site.yml:483-495; roles/keystone/tasks/deploy.yml:1-15, roles/keystone/tasks/bootstrap_service.yml:33-51, roles/keystone/tasks/distribute_fernet.yml:12-18, roles/keystone/templates/fernet-push.sh.j2:20, roles/keystone/handlers/main.yml:2-98; Keystone; fact sheet B §3.5, §3.6, §3.7, §3.9 items 1–2

R20 — Glance reconfigure / deploy

Still applies to 2024.1 CODE.

Operation / trigger Glance reconfigure / deploy
What actually happens toggles global MariaDB log_bin_trust_function_creators 1→0 around db sync (unless use_preconfigured_databases); with the file backend on the default named volume (glance_file_datadir_volume: "glance") only the first glance-api host runs glance-api → any restart is a full Image API outage
Blast radius DB + glance
VM impact NOT AVAILABLE whether snapshots in progress fail
API impact Image API outage
Likelihood Certain
Severity Medium
Precautions Avoid during image-heavy operations
Evidence roles/glance/tasks/bootstrap_service.yml:2-54; group_vars/all.yml:1001,1007,1011; roles/glance/defaults/main.yml:6, :86; Glance; fact sheet C §1

R21 — Enabling Swift (or glance_backend_ceph) on a running cloud

Still applies to 2024.1 CODE; the new S3 backend (glance_backend_s3) takes part in the same switch.

Operation / trigger Enabling Swift (or setting glance_backend_ceph, glance_backend_s3 or glance_backend_vmware) on a running cloud
What actually happens silently switches Glance's backend (glance_backend_swift follows enable_swift, and glance_backend_file becomes false as soon as any other backend is on); NOT AVAILABLE whether existing file-store images stay readable
Blast radius glance
VM impact NOT AVAILABLE whether boots from existing images fail
API impact yes
Likelihood High
Severity High
Precautions Set glance_backend_* explicitly before enabling Swift
Evidence group_vars/all.yml:842, :1001-1006; fact sheet C §1.8

R22 — Inventory reordering

Still applies to 2024.1 CODE.

Operation / trigger Inventory reordering (loadbalancer, mariadb, glance, nova-conductor, keystone groups)
What actually happens keepalived priorities change (priority = position in loadbalancer + 1); the MariaDB active HAProxy backend moves (first host of the default shard); glance moves (file backend: first glance-api host); bootstrap/discovery targets (groups[...][0], e.g. cell creation on the first nova-conductor host, fernet push fallback to the first keystone host) change
Blast radius per group
VM impact indirect
API impact possible
Likelihood Medium
Severity High
Precautions Treat inventory order as configuration; never reorder casually
Evidence roles/loadbalancer/templates/keepalived/keepalived.conf.j2:15; roles/mariadb/defaults/main.yml:64, group_vars/all.yml:477, :1011; roles/nova-cell/tasks/create_cells.yml:4, :28; roles/keystone/tasks/distribute_fernet.yml:16-18; fact sheets A §1.8, B §1.2, §1.5, C §1

R23 — Any run with --limit on a large inventory

Still applies to 2024.1 CODE (F9).

Operation / trigger Any run with --limit on a large inventory
What actually happens fact gathering for all hosts is executed sequentially by the limited hosts (delegated loop) → long runtime; cross-host files are not updated on non-limited hosts
Blast radius –
VM impact none
API impact none
Likelihood Certain
Severity Low (time), Medium (drift)
Precautions Enable fact caching (ansible-tuning.rst, section "Fact caching"); follow up with a full run when cross-host config changed
Evidence gather-facts.yml:34-62 (each limited host loops over its share of groups['all']: one delegated setup per host without facts); ansible-core 2.16.20 lib/ansible/executor/task_executor.py:259-413 (loop items run one after another, :288); doc/source/user/ansible-tuning.rst:36-60

R24 — Effective container stop timeout is 10 s

No longer holds as written in 2024.1 CODE, as in 2023.1: containers (except one-shot ones) run under a systemd unit kolla-<name>-container.service whose ExecStop is /usr/bin/<engine> stop <name> -t <graceful_timeout> (docker or podman), and graceful_timeout comes from docker_common_options, i.e. docker_graceful_timeout (60 s). The 10 s value remains only as the module default when no graceful_timeout is passed, which plays using docker_common_options do not hit (F3).

Operation / trigger Any container restart or stop (recreate_or_restart_container, restart_container, stop_container)
What actually happens the restart goes through systemd RestartUnit/StopUnit; <engine> stop -t 60 sends SIGTERM and kills a service still running after 60 s (heat-engine, cinder-volume copies, glance uploads); the module waits up to client_timeout (docker_client_timeout: 120 s) for the unit state and fails with "Container timed out" otherwise. A stop uses the timeout written in the existing unit file; a restart rewrites the unit first. Changing docker_graceful_timeout changes the unit text, so the next check restarts every long-running container whose role runs a check task (Swift deploy does not) (R26). NOT AVAILABLE systemd's own stop timeout for these units (the unit sets none, and systemd defaults are not in these sources). NOT AVAILABLE Whether services started by a shell wrapper that does not exec them (e.g. neutron-l3-agent, haproxy, ovs-vswitchd, ovsdb-server) receive SIGTERM at all (Kolla images §2.6)
Blast radius all restarts
VM impact in-flight operations killed after 60 s
API impact –
Likelihood Certain
Severity Medium
Precautions Drain long operations before restarts; raise docker_graceful_timeout if needed (it reaches the unit on the next restart, and restarts every container whose unit it changes)
Evidence module_utils/kolla_systemd_worker.py:20-39, :42-87, :97-125, :149-185, :205-216; module_utils/kolla_docker_worker.py:341-363, :415-459; library/kolla_container.py:361-373; group_vars/all.yml:105,139,142-153; Repository architecture §6; kolla docker/base/Dockerfile.j2:370, docker/base/start.sh:24; roles/neutron/templates/neutron-l3-agent-wrapper.sh.j2:16, roles/openvswitch/templates/start-ovs.j2:2

R25 — -t common believed to reconfigure fluentd/cron

Does not apply to 2024.1 CODE, as in 2023.1: common is the Apply role common play in site.yml, with play-level tags: common, so -t common runs its tasks on the cron, fluentd, kolla-logs and kolla-toolbox hosts (F2). There is still no chrony role (the Ussuri workaround -t chrony).

Operation / trigger -t common believed to reconfigure fluentd/cron
What actually happens -t common does reconfigure fluentd, cron and kolla_toolbox (config → check-containers → handlers), and in 2024.1 its config step also makes sure the fluentd image is present. The reverse surprise exists instead: a tagged service run (e.g. -t nova) does not run the common play, so a fluentd/logrotate change waits for an untagged or -t common run (R2)
Blast radius the common hosts
VM impact –
API impact –
Likelihood Does not apply in 2024.1
Severity –
Precautions Use -t common to apply fluentd/cron changes; verify with docker exec … kolla_set_configs --check
Evidence site.yml:88-103; roles/common/tasks/main.yml:1-2, roles/common/tasks/deploy.yml:1-9, roles/common/tasks/config.yml:42-51; Tags §2.1

R26 — First 2024.1 deploy/reconfigure on containers whose unit 2023.1 wrote

New in 2024.1 CODE (F16).

Operation / trigger The first 2024.1 run that checks a container whose kolla-<name>-container.service unit was written by 2023.1 code and that no 2024.1 run has created, recreated or restarted yet: e.g. a service left out of a tagged or --limit upgrade, then any deploy, reconfigure, deploy-containers or upgrade that reaches its role. Later, any change of docker_graceful_timeout, docker_client_timeout, docker_restart_policy_retry, or of docker_restart_policy to a value that renders differently, has the same effect (unless-stopped and always both render Restart=always)
What actually happens compare_container reports drift when check_unit_change finds that the unit file on disk differs from the rendered template, whole text compared. The 2024.1 template writes StartLimitInterval= where 2023.1 wrote StartLimitIntervalSec= followed by a blank line; with Docker the other lines render as in 2023.1 (the 2023.1 template hard-coded docker; 2024.1 names the engine, which is docker here), so this one line makes every such unit differ. Check <role> containers then notifies the restart handlers, and through loop-notify every container of that role on that host; with COPY_ALWAYS, restart_container rewrites the unit, reloads systemd, enables the unit and restarts it (the loadbalancer handlers stop and start instead, and start_container writes the new unit). A container that a 2024.1 run creates, recreates or restarts (an upgrade that reaches its role does one of these) gets the new unit then and is not flagged again; one-shot containers have no unit. Swift has no check task: its deploy calls start_container, which does not compare the unit, so a running Swift container keeps its 2023.1 unit (its reconfigure restarts every Swift container anyway)
Blast radius every host of the run, role by role; on computes nova_libvirt and, through the openvswitch role, openvswitch_vswitchd
VM impact as R1 and R7 for the containers concerned; NOT AVAILABLE whether running VMs or their traffic are affected
API impact the restarted services; NOT AVAILABLE for how long
Likelihood Certain (for such containers)
Severity High
Precautions After an upgrade from 2023.1, treat the first deploy/reconfigure of every role the upgrade did not reach as a restart of that role: run it per role (-t), in --limit batches or with ANSIBLE_SERIAL / -e kolla_serial, OVS hosts one at a time; prefer an untagged upgrade, which recreates every container whose image changed and, through the unit check, restarts those whose image did not. Treat a change of the docker_* timeouts or restart policy the same way
Evidence module_utils/kolla_systemd_worker.py:20-39 (template), :50-54 (engine dependency), :154-167 (check_unit_change: whole text), :172-185 (create_unit_file: write, reload, enable); module_utils/kolla_container_worker.py:58-65 (compare_container); module_utils/kolla_podman_worker.py:294-301 (same for Podman); module_utils/kolla_docker_worker.py:334-339 (unit written at creation, none for a one-shot), :341-363, :365-389 (start_container: unit written only when the container is not up), :439-459; module_utils/kolla_systemd_worker.py:56-58 (unless-stopped becomes always); group_vars/all.yml:105,117,120,139,142-153; e.g. roles/nova-cell/tasks/check-containers.yml:2-22, roles/openvswitch/tasks/check-containers.yml:2-18; roles/swift/tasks/deploy.yml:1-10, roles/swift/tasks/start.yml:36-49; roles/loadbalancer/handlers/main.yml:54-68; 2023.1 template: 2023.1 kolla-ansible tree, ansible/module_utils/kolla_systemd_worker.py, lines 20-40 (TEMPLATE hard-codes docker); Repository architecture §6

R27 — Quorum-queue default on a cloud with classic queues

New in 2024.1 CODE (F17).

Operation / trigger The first 2024.1 upgrade, deploy or reconfigure on a cloud that kept the 2023.1 RabbitMQ defaults (om_enable_rabbitmq_high_availability: false, om_enable_rabbitmq_quorum_queues: false) and does not set them in globals.yml; also kolla-ansible prechecks on such a cloud
What actually happens om_enable_rabbitmq_quorum_queues now defaults to true, so every service template that renders [oslo_messaging_rabbit] writes rabbit_quorum_queue = true (26 templates in 24 roles, e.g. nova, nova-cell, neutron): the config changes and those services restart when their plays run, computes included (nova-cell's nova.conf, neutron's neutron.conf), with the reach of R3. The RabbitMQ role removes the ha-all policy on deploy, reconfigure and upgrade when HA is off. prechecks fails when HA and quorum are equal (so also when both are set to false), and, when a rabbitmq container exists and quorum is on, asserts that every queue except reply_ and _fanout ones is a quorum queue, so it fails while classic queues exist; its message calls the migration manual. upgrade, deploy and reconfigure do not run these checks. NOT AVAILABLE What oslo.messaging does with existing classic queues when the services restart with rabbit_quorum_queue = true
Blast radius all hosts that run a messaging service
VM impact as R1 plus neutron agent restart; NOT AVAILABLE their effect on VMs
API impact NOT AVAILABLE whether RPC fails while queues are redeclared
Likelihood Certain (default kept)
Severity High
Precautions Run prechecks before the upgrade (the 2024.1 docs recommend it); decide on the queue type first: migrate to quorum queues, or keep classic queues with om_enable_rabbitmq_high_availability: true and the ha-all policy in place, the only classic-queue setting that passes prechecks. On a cloud that kept the 2023.1 default (HA off), 2023.1 runs removed ha-all (2023.1 kolla-ansible tree: ansible/roles/rabbitmq/tasks/deploy.yml, lines 4-6), so this path too needs the manual migration that the HA precheck message describes (roles/rabbitmq/tasks/precheck.yml:115-123); then roll the messaging config out like R3
Evidence group_vars/all.yml:266-279; roles/nova-cell/templates/nova.conf.j2:207-216, roles/neutron/templates/neutron.conf.j2:146-155; roles/rabbitmq/tasks/deploy.yml:4-6, roles/rabbitmq/tasks/upgrade.yml:4-6, roles/rabbitmq/tasks/remove-ha-all-policy.yml:18-22; roles/prechecks/tasks/service_checks.yml:67-81; roles/rabbitmq/tasks/precheck.yml:107-129, :131-189; site.yml:77-86 (the prechecks play runs only for kolla_action precheck), tools/kolla-ansible:444-447; doc/source/user/operating-kolla.rst:170-175; RabbitMQ

R28 — upgrade with RabbitMQ more than one minor version behind

New in 2024.1 CODE: upgrade.yml now imports version-check.yml (deploy and reconfigure already did in 2023.1).

Operation / trigger kolla-ansible upgrade (or deploy/reconfigure) while the running RabbitMQ is more than one minor version behind the target image, e.g. a cloud still on the 2023.1 default image (RabbitMQ 3.11) against the 2024.1 one (3.13)
What actually happens when a rabbitmq container exists, once on the first host of the group (run_once), the check reads the running version with rabbitmqctl --version and the new one from a one-shot rabbitmq_version_check container of the target image, then asserts at most one minor version between them (or 3.13 → 4.0/4.1); a second assert refuses a downgrade. Under --check none of this runs: the Get container facts task that gates the block has no check_mode: false, and kolla_container_facts declares no check-mode support, so it is skipped and the block's condition is false (the one-shot task's own check_mode: false is never reached). A failed run_once task fails every host of the play, so the whole batch fails and ansible-core ends the playbook. The RabbitMQ plays come after the common, loadbalancer, redis, MariaDB, memcached and other plays of site.yml, which an untagged run has already applied. The 2024.1 kolla tree has no rabbitmq-3-12 image (only rabbitmq and rabbitmq-4-1). NOT AVAILABLE Which version a given cloud runs, and which image a rabbitmq-upgrade 3.12 run would find in the registry
Blast radius the run: every play after the RabbitMQ play is not applied
VM impact none directly; NOT AVAILABLE the effect of a cloud left half-upgraded
API impact NOT AVAILABLE
Likelihood Certain for a cloud still on the 2023.1 default RabbitMQ image (3.11); otherwise NOT AVAILABLE (depends on the running version)
Severity High
Precautions Before the upgrade, read the running RabbitMQ version (rabbitmqctl --version); step it with kolla-ansible rabbitmq-upgrade <version> first, as the failure message and the docs ("SLURP extra preparations") say. Running the upgrade with -t rabbitmq first does not replace that step: it runs the same check and fails the same way on a skip, but before any other play has run. --skip-tags rabbitmq-version-check skips the check entirely
Evidence roles/rabbitmq/tasks/upgrade.yml:2, roles/rabbitmq/tasks/version-check.yml:2-82 (asserts at :44-64 and :66-73, tag at :79); site.yml:468, :88-466 (earlier plays); ansible-core 2.16.20 lib/ansible/plugins/strategy/__init__.py:598-602 (run_once failure marks every host failed), lib/ansible/executor/playbook_executor.py:207-209, :219-220; kolla docker/rabbitmq/rabbitmq/apt_preferences_rabbitmq.ubuntu:1-3, docker/rabbitmq/rabbitmq/rabbitmq_packages_rpm.rocky:1-4; 3.11 in 2023.1: 2023.1 kolla tree, docker/rabbitmq/rabbitmq/apt_preferences_rabbitmq.ubuntu, line 2 (Pin: version 3.11.*); roles/rabbitmq/tasks/version-check.yml:3-9, :36, :75 (facts task, one-shot check_mode: false, block condition); library/kolla_container_facts.py:120 (no supports_check_mode); ansible-core 2.16.20 lib/ansible/module_utils/basic.py:506-507 (such a module is skipped under --check); rabbitmq.yml:12-13 (play tag rabbitmq); rabbitmq-upgrade.yml:18-21; doc/source/user/operating-kolla.rst:179-187; RabbitMQ

R29 — HAProxy frontend change written by genconfig

New in this register CODE: the mechanism is not specific to 2024.1, but no earlier entry covered it.

Operation / trigger A change that alters a service's HAProxy frontend (port, TLS, external FQDN, single external frontend), written first with genconfig (kolla_action=config), then applied with -t <svc> reconfigure or -t <svc> deploy-containers
What actually happens genconfig runs the service includes of the loadbalancer play (kolla_action config is in their list), and each service's loadbalancer.yml imports loadbalancer-config with tags: always, so /etc/kolla/haproxy/services.d/<svc>.cfg (and the external-frontend-map block) are rewritten. Their notify: Restart haproxy container is lost: every stop and start handler of the loadbalancer role is skipped under config. A later -t <svc> reconfigure finds the file unchanged and notifies nothing; deploy-containers runs no loadbalancer include. HAProxy keeps the old frontend until -t haproxy reconfigure or an untagged run, whose check compares services.d and restarts HAProxy (staged, R8)
Blast radius the service's API (old frontend)
VM impact none
API impact the old frontend stays live; NOT AVAILABLE whether clients fail against it
Likelihood High (with genconfig)
Severity Medium (drift), then R8 at the next untagged run
Precautions Copy /etc/kolla/haproxy/services.d/ before genconfig and diff after; apply a frontend change deliberately with -t haproxy reconfigure (staged restart, R8)
Evidence tools/kolla-ansible:557-560; site.yml:105-327 (service includes, condition at :324-326); e.g. roles/nova/tasks/loadbalancer.yml:2-7; roles/loadbalancer-config/tasks/main.yml:2-4; roles/haproxy-config/tasks/main.yml:2-23, :25-53; roles/loadbalancer/handlers/main.yml:9-34 (kolla_action != "config" at :16-17); roles/loadbalancer/templates/haproxy/haproxy.json.j2:17, roles/loadbalancer/tasks/check-containers.yml:2-18; Predict and inspect a run; Controlled batches

R30 — Octavia with the amphora provider and no Redis

New in 2024.1 CODE.

Operation / trigger prechecks, deploy, reconfigure or upgrade with enable_octavia: yes, the default amphora provider, and enable_redis left at no
What actually happens enable_octavia_jobboard is on by default with the amphora provider, so octavia.conf gets a [task_flow] section whose jobboard_backend_hosts lists the redis group, and a persistence_connection to a new octavia_persistence database, which upgrade creates. prechecks fails with "Redis must be enabled when using octavia jobboard"; deploy, reconfigure and upgrade do not run that assert and render the section whether or not the redis play runs (it runs only where enable_redis is true). NOT AVAILABLE How Octavia behaves when the jobboard points at hosts with no Redis
Blast radius Octavia (load balancer create/update)
VM impact NOT AVAILABLE for amphora instances
API impact NOT AVAILABLE
Likelihood Certain (default)
Severity Medium
Precautions Before the upgrade, choose: enable_redis: yes (Redis is deployed by its own play, before Octavia) or enable_octavia_jobboard: no; make sure passwords.yml has octavia_persistence_database_password; run prechecks
Evidence group_vars/all.yml:830-840; roles/octavia/defaults/main.yml:386; roles/octavia/templates/octavia.conf.j2:177-189; roles/octavia/tasks/precheck.yml:67-73; roles/octavia/tasks/upgrade.yml:6-41; site.yml:384-396; Octavia

Heat map (likelihood × severity)

quadrantChart
  title Risk heat map (relative)
  x-axis Low likelihood --> High likelihood
  y-axis Low severity --> High severity
  quadrant-1 Prevent or control strictly
  quadrant-2 Prepare contingency
  quadrant-3 Accept
  quadrant-4 Standardise procedure
  R1 nova compute change: [0.85, 0.75]
  R3 RabbitMQ membership: [0.9, 0.8]
  R5 ml2 override: [0.8, 0.45]
  R7 OVS restart: [0.6, 0.95]
  R8 HAProxy restart: [0.75, 0.65]
  R12 tag change via deploy: [0.55, 0.93]
  R14 bootstrap servers rerun: [0.4, 0.88]
  R16 destroy: [0.05, 0.98]
  R11 pull: [0.9, 0.15]
  R24 60s stop timeout: [0.95, 0.45]
  R26 first run unit drift: [0.8, 0.7]
  R27 quorum default: [0.88, 0.72]
  R28 RabbitMQ version gate: [0.86, 0.66]
  R29 genconfig frontends: [0.7, 0.4]
  R30 Octavia without Redis: [0.65, 0.5]

R25 is left out of the heat map: it does not apply to 2024.1.

To remember

Lumo: if you keep only 5 things from this page, keep these.

  • Rated Critical: openvswitch_vswitchd restart or recreate (R7), image tag change run with deploy instead of upgrade (R12), bootstrap-servers re-run (R14), stop (R15), destroy (R16).
  • A config change touching nova-compute, then deploy/reconfigure, restarts nova_compute, nova_libvirt and nova_ssh on every affected compute, all at once with the default serial 0; whether running VMs keep running is NOT AVAILABLE. CODE
  • New in 2024.1 (R26): the systemd unit template changed, so the first 2024.1 deploy/reconfigure restarts every container whose unit 2023.1 wrote and that no 2024.1 run has created, recreated or restarted yet, in every role with a Check <role> containers task (all site.yml roles except Swift, whose deploy does not compare the unit). CODE
  • New in 2024.1 (R27): quorum queues are on by default, so every messaging service's config changes and restarts on the first 2024.1 run, computes included, and prechecks fails while classic queues exist. CODE
  • New in 2024.1 (R28): upgrade runs the RabbitMQ version check; a broker more than one minor version behind stops the playbook at the RabbitMQ play, after the plays before it have run. CODE

What would you do?

Lumo: a situation you could meet on a real platform, and three ways to react. Pick the one you would choose: I will tell you what this page says about it. Nothing is recorded.

Scenario 1: A new image tag on a running cloud

You must move your production cloud to a new openstack_tag. A colleague has already changed the tag in globals.yml and proposes to run kolla-ansible deploy, "since deploy is idempotent anyway".

What would you do?

See every choice explained
  • Avoid: Run kolla-ansible deploy with the new tag, as proposed.. This is R12, rated Critical CODE: every container is recreated (fleet-wide), and the upgrade-only steps (the nova-status check, the reload plays, the online data migrations, except Placement's) do not run. For Neutron, bootstrap_neutron runs neutron-db-manage … upgrade head with the new image before the handlers restart the old neutron_server containers.
  • Works, but risky: Run kolla-ansible upgrade on the whole cloud at once, with no tag and no serial, and let each host fetch its images.. upgrade is the right action, but this skips the precautions the register gives for R12: pull then upgrade, per-service tags, ANSIBLE_SERIAL. It also skips the checks R27 and R28 ask for before an upgrade from 2023.1.
  • Best choice: Run kolla-ansible pull and prechecks first, check the RabbitMQ version and queue type, then upgrade with per-service tags and ANSIBLE_SERIAL.. These are the precautions for R12 (pull then upgrade, as the 2024.1 docs say; per-service tags; ANSIBLE_SERIAL), plus the 2024.1 ones: prechecks for the quorum-queue checks (R27) and the RabbitMQ version step before the upgrade (R28).

Read the section.

Scenario 2: The first reconfigure after the upgrade

Your cloud was upgraded from 2023.1 to 2024.1 last week with -t limited runs, service by service; the Neutron and Open vSwitch roles were left out of it. Today you must change one Keystone option, and a colleague plans an untagged kolla-ansible reconfigure in business hours, "since only keystone.conf changes".

What would you do?

See every choice explained
  • Avoid: Run the untagged reconfigure as planned.. This is R26 CODE: the unit text is part of the container check, and the 2024.1 template differs from the 2023.1 one, so every container still running under a 2023.1 unit, openvswitch_vswitchd included (R7), is restarted on every host of the run; with the default serial 0 each role restarts on all its hosts in one batch, play after play (RabbitMQ, MariaDB and the loadbalancer stage their own restarts).
  • Best choice: Run -t keystone reconfigure only, and plan the rest of the fleet as a restart window with --limit batches.. A Keystone tag keeps the run to the Keystone play and Keystone's HAProxy include (R19); the containers whose unit no 2024.1 run has rewritten yet (here those of the Neutron and Open vSwitch roles) will restart at their next check, so that check is planned like an image change: per role, in batches, OVS hosts one at a time (R26, R7).
  • Works, but risky: Run the untagged reconfigure with ANSIBLE_SERIAL=1.. Serial bounds each batch to one host, but the run still restarts every checked container with a 2023.1 unit on every host, Open vSwitch and nova_libvirt included, which is far more than the Keystone change (R26).

Read the section.

Scenario 3: Prechecks fail on the queues

Before the upgrade to 2024.1, kolla-ansible prechecks fails with "om_enable_rabbitmq_quorum_queues is True but … is a non-quorum queue". Your globals.yml does not set any om_enable_rabbitmq_* option. A colleague wants to skip the tag rabbitmq-ha-precheck and run upgrade.

What would you do?

See every choice explained
  • Avoid: Skip the precheck tag and upgrade with the defaults.. This is R27 CODE: the upgrade renders rabbit_quorum_queue = true for every messaging service, computes included, and restarts them; what oslo.messaging then does with the existing classic queues is NOT AVAILABLE.
  • Best choice: Decide on the queue type first: migrate the queues to quorum (a manual procedure, per the precheck message), or keep classic queues with om_enable_rabbitmq_high_availability: true and the ha-all policy, then rerun prechecks.. The precheck fails when HA and quorum are equal, so setting quorum to false alone does not pass; the only classic-queue setting that passes is HA on with the ha-all policy in place; on a cloud that kept the 2023.1 default (HA off) 2023.1 runs removed that policy, so this path is also a manual migration, as the HA precheck message says, and HA on also renders amqp_durable_queues = true in the service configs (R27).
  • Avoid: Set om_enable_rabbitmq_quorum_queues: false and rerun prechecks.. It never passes prechecks: the variable check fails when HA and quorum are equal, both off included CODE. It would also keep classic non-mirrored queues (R27).

Read the section.

Check yourself

Lumo: 4 quick questions to check the main ideas of this page. Choose an answer to see the explanation and the section that gives the evidence. Your score counts your first choices and stays in this browser only.

1. Which of these operations is rated Critical?
Show the answer

Answer: kolla-ansible stop (R15). The risks rated Critical are R7, R12, R14, R15 and R16. genconfig restarts nothing; its risk (R29) is drift. Read the section.

2. A nova-compute config change is applied by reconfigure with the default serial 0. What restarts?
Show the answer

Answer: nova_compute, nova_libvirt and nova_ssh on every affected compute, all at once. This is risk R1 (loop-notify, serial 0 = one batch). Read the section.

3. After an upgrade from 2023.1, a deploy runs on a host whose neutron_openvswitch_agent was left out of the upgrade, so no 2024.1 run has recreated or restarted it. Its config did not change. Is it restarted?
Show the answer

Answer: Yes: its unit file was written by 2023.1, and the 2024.1 check compares the unit text. This is R26 (F16): compare_container includes check_unit_change, which compares the whole unit text. Read the section.

4. An upgrade fails the RabbitMQ version check. What has already happened?
Show the answer

Answer: The plays before the RabbitMQ play (common, loadbalancer, MariaDB, memcached, …) have already run. The check is inside the RabbitMQ role, whose plays come after those in site.yml; a failed run_once assert fails every host of the play and ends the playbook (R28). Read the section.