Risk register

Potentially dangerous operations on a running Kolla-Ansible Ussuri platform: their impact and the precautions to take before running them. Ratings are relative to a production cloud with running VMs.

Note

Key answers

  • 25 risks (R1–R25), each with what actually happens, its blast radius, VM and API impact, likelihood, severity, precautions and evidence (Matrix).
  • Rated Critical: R7 (openvswitch_vswitchd restart or recreate), R12 (changing the image tag and running deploy instead of upgrade), R14 (bootstrap-servers re-run on a live host), R15 (kolla-ansible stop) and R16 (kolla-ansible destroy).
  • Computes and VMs: R1. Any config change touching nova-compute, followed by a deploy/reconfigure with a nova tag or no tag, restarts nova_compute, nova_libvirt and nova_ssh on every affected compute, all at once with the default serial 0; whether live migrations in flight fail and whether running VMs keep running are NOT AVAILABLE.
  • Network data plane: R5 (an ml2_conf.ini override restarts every OVS agent), R6 (with enable_neutron_agent_ha: yes, the L3 agent wrapper runs neutron-netns-cleanup --force --agent-type l3 before the agent starts) and R7; whether VM traffic is interrupted is NOT AVAILABLE.
  • Likelihood × severity at a glance: the heat map.
  • Likelihood = how likely the operation is to cause the impact when the triggering condition is present.
  • Severity = worst realistic outcome.
  • Evidence cites the source lines, or the study section that cites them. Nothing was run. NOT AVAILABLE marks outcomes that the sources do not establish.

Matrix

# Risk Likelihood Severity
R1 Config change touching nova-compute High High
R2 Enabling or disabling a service with a logrotate or fluentd entry High Medium–High
R3 Changing RabbitMQ membership, password or port Certain High
R4 Changing memcached membership Certain High
R5 ml2_conf.ini override meant for neutron-server Certain High
R6 neutron_l3_agent restart with enable_neutron_agent_ha: yes Certain (if HA flag) High
R7 openvswitch_vswitchd restart or recreate Certain on image change Critical
R8 HAProxy config change Certain if changed High
R9 MariaDB config change or image change Certain if changed High
R10 RabbitMQ image change (upgrade) Certain on upgrade High
R11 kolla-ansible pull – Low (bandwidth)
R12 Image tag change run with deploy instead of upgrade Certain Critical
R13 Rebuilt image under the same tag, then deploy/reconfigure without pull – Medium (drift)
R14 bootstrap-servers re-run on a live host Medium Critical
R15 kolla-ansible stop Certain Critical
R16 kolla-ansible destroy Certain Critical
R17 prune-images Low Low
R18 mariadb_recovery Certain High
R19 Keystone reconfigure Certain if changed Medium–High
R20 Glance reconfigure / deploy Certain Medium
R21 Enabling Swift (or glance_backend_ceph) on a running cloud High High
R22 Inventory reordering Medium High
R23 Any run with --limit on a large inventory Certain Low (time), Medium (drift)
R24 Effective container stop timeout is 10 s Certain Medium
R25 -t common believed to reconfigure fluentd/cron Certain Low–Medium (surprise)

R1 — Config change touching nova-compute

Operation / trigger Any config change touching nova-compute (override, global flag, password, RabbitMQ list) followed by deploy/reconfigure with a nova tag or no tag
What actually happens nova_compute and nova_libvirt and nova_ssh restart on every affected compute, all at once (serial 0). The cause is the loop-notify behaviour
Blast radius all computes
VM impact libvirtd restart; NOT AVAILABLE whether live migrations in flight fail and whether running VMs keep running
API impact nova-compute restarts on each host; NOT AVAILABLE how long it is down
Likelihood High
Severity High
Precautions genconfig + diff, then deploy-containers --limit in batches, or ANSIBLE_SERIAL; drain live migrations first; validate libvirt restart behaviour in staging
Evidence roles/nova-cell/tasks/check-containers.yml:2-20, roles/nova-cell/defaults/main.yml:3-54, nova.yml:132; ansible 2.9.27 lib/ansible/executor/playbook_executor.py:276-278 (serial 0 = one batch); Tags §2.4; Nova deep dive §5

R2 — Enabling or disabling a service with a logrotate or fluentd entry

Operation / trigger Enabling or disabling a service that has a logrotate or fluentd input entry (enable_X for most OpenStack services, e.g. barbican) in globals.yml, then running any play that includes common
What actually happens td-agent.conf and logrotate.conf render differently on every host → fluentd, cron and kolla_toolbox restart (loop-notify) on every host where a play that runs common executes: the whole fleet for an untagged run, only the tagged service's hosts for a tagged run (-t nova with the multinode inventory: the control and compute hosts, which the nova.yml plays target; the others keep the old files until a later run includes common there). Nova/Cinder/Glance configs gain sections (e.g. [barbican]) → those services restart too. Flags in neither list (e.g. enable_prometheus, enable_ovn, enable_openvswitch, enable_memcached, enable_placement, enable_redis) leave both files unchanged
Blast radius fleet-wide (untagged run); the service's hosts (tagged run)
VM impact fluentd, cron and kolla_toolbox are none of the containers that Tags §3.1 traces to running VMs CODE; NOT AVAILABLE whether their restart affects VMs another way (Apply common changes (fluentd, cron, kolla_toolbox) §3); Nova restarts as R1
API impact the services whose configs changed restart (stop up to 10 s, then start; R24); NOT AVAILABLE how long their APIs are unavailable, and whether the fluentd, cron and kolla_toolbox restarts affect APIs (Apply common changes (fluentd, cron, kolla_toolbox) §3)
Likelihood High
Severity Medium–High
Precautions Treat enable_* changes as fleet-wide changes. Roll out with --limit batches
Evidence roles/common/tasks/config.yml:109-240, roles/common/defaults/main.yml:105-187, roles/common/tasks/check-containers.yml:2-17 (loop-notify, Tags §2.4); roles/nova-cell/templates/nova.conf.j2:234-239; site.yml:132-133, nova.yml:29-132, inventory/multinode:138-139,287-309

R3 — Changing RabbitMQ membership, password or port

Operation / trigger Changing RabbitMQ group membership (adding/removing a controller), RabbitMQ password or port
What actually happens rpc_transport_url changes in every messaging service on every host → all nova, neutron (and any compute-side agent) containers restart; update_cell rewrites the cell's MQ URL
Blast radius all hosts
VM impact as R1 plus neutron agent restart; NOT AVAILABLE its effect on flows
API impact yes
Likelihood Certain
Severity High
Precautions Plan as a maintenance; batch with --limit; verify RabbitMQ cluster health first
Evidence group_vars/all.yml:206,216; roles/nova-cell/tasks/create_cells.yml:31-55; loop-notify (Tags §2.4)

R4 — Changing memcached membership

Operation / trigger Changing memcached membership
What actually happens 38 roles embed the memcached host list in their configs (37 template loops plus monasca's monasca_memcached_servers; fact sheet B §3.10 counts 36, corrected in Per-role fact sheets), so their services restart when their plays run; NOT AVAILABLE whether cached tokens are lost. Not only the control plane: neutron.conf is shared by every neutron agent, so neutron_openvswitch_agent restarts on every compute and network node, and the dhcp, l3 and metadata agents, which get the same file, restart on network nodes; cinder.conf reaches cinder-volume/backup and ceilometer.conf ceilometer-compute. Compute nova.conf has no memcached list
Blast radius controllers + network nodes + all computes (+ storage)
VM impact as R5: OVS agent restart; NOT AVAILABLE its effect on flows, and whether router/DHCP traffic is interrupted on network nodes; with enable_neutron_agent_ha, the R6 netns cleanup
API impact memcached server list changes; NOT AVAILABLE effect on auth latency and Horizon sessions
Likelihood Certain
Severity High
Precautions Plan as a dataplane change, like R3/R5: batch with --limit or ANSIBLE_SERIAL, network nodes one at a time; low-traffic window
Evidence fact sheet B §3.9 item 2, §3.10; roles/neutron/templates/neutron.conf.j2:119, roles/neutron/tasks/config.yml:73-98

R5 — ml2_conf.ini override meant for neutron-server

Operation / trigger /etc/kolla/config/neutron/ml2_conf.ini override (meant for neutron-server)
What actually happens also merged into openvswitch_agent.ini → every OVS agent restarts (computes + network). On network nodes, loop-notify also restarts dhcp, l3 and metadata agents
Blast radius network + all computes
VM impact OVS agent restart; NOT AVAILABLE its effect on flows, and whether router/DHCP traffic is interrupted on network nodes
API impact neutron-server restart
Likelihood Certain
Severity High
Precautions Put server-only options in neutron/neutron-server.conf, or check the rendered openvswitch_agent.ini diff
Evidence roles/neutron/tasks/config.yml:172-190, roles/neutron/tasks/check-containers.yml:2-18 (loop-notify, Tags §2.4)

R6 — neutron_l3_agent restart with enable_neutron_agent_ha: yes

Operation / trigger Any restart of neutron_l3_agent with enable_neutron_agent_ha: yes
What actually happens the wrapper runs neutron-netns-cleanup --force --agent-type l3 before the agent starts (the wrapper's comment: "Remove all l3 related netns"), then neutron-l3-agent starts CODE. NOT AVAILABLE What the command deletes: it is neutron code, which is not in these sources (F12)
Blast radius network nodes (and DVR computes)
VM impact NOT AVAILABLE whether north-south and floating-IP traffic of the routers on that node stops, whether and when neutron-l3-agent rebuilds the namespaces, and whether HA routers fail over
API impact none
Likelihood Certain (if HA flag)
Severity High
Precautions Restart network nodes one at a time; fail routers over first
Evidence roles/neutron/templates/neutron-l3-agent-wrapper.sh.j2:5-18

R7 — openvswitch_vswitchd restart or recreate

Operation / trigger openvswitch_vswitchd restart or recreate (image change, start-ovs change, -t openvswitch with a changed image; also any openvswitch_db-only drift, e.g. a start-ovsdb-server change or a db image, volume or dimension change: check-containers loops over both OVS services, so loop-notify (Tags §2.4) also notifies the vswitchd handler, which runs after the db restart and wait)
What actually happens ovs-vswitchd (the userspace daemon) restarts. The image only runs modprobe openvswitch (the kernel module is loaded, never unloaded or reloaded), and start-ovs launches ovs-vswitchd with no flow save/restore. Bridges and ports persist in conf.db on the openvswitch_db volume. NOT AVAILABLE Whether the OpenFlow tables held by the old daemon are lost, and whether neutron-openvswitch-agent (or ovn-controller with OVN) reprograms them
Blast radius per host (all OVS hosts at once with serial 0)
VM impact NOT AVAILABLE whether all VM network traffic on the host is interrupted until flows are restored, and for how long
API impact none
Likelihood Certain on image change
Severity Critical
Precautions Upgrade or recreate OVS host by host with evacuation or acceptance; never fleet-wide with serial 0
Evidence roles/openvswitch/handlers/main.yml:2-42, roles/openvswitch/tasks/check-containers.yml:2-17, roles/openvswitch/templates/start-ovs.j2:2, roles/openvswitch/defaults/main.yml:59; kolla docker/openvswitch/openvswitch-vswitchd/extend_start.sh:3; Kolla images §5

R8 — HAProxy config change

Operation / trigger HAProxy config change (any service frontend, certs, haproxy.cfg)
What actually happens haproxy restarted (never reloaded) on all haproxy hosts at once; NOT AVAILABLE whether keepalived drops or moves the VIP, and for how long
Blast radius all APIs + all DB traffic (DB address is the VIP)
VM impact none directly; NOT AVAILABLE whether nova/neutron get DB errors while haproxy restarts
API impact yes
Likelihood Certain if changed
Severity High
Precautions ANSIBLE_SERIAL=1 for haproxy changes; --skip-tags haproxy when you don't intend to change frontends
Evidence fact sheet A §1.8

R9 — MariaDB config change or image change

Operation / trigger MariaDB config change or image change
What actually happens rolling restart in 4 waves by index % 4, one wave after another; each wave waits up to 10 × 6 s for WSREP Synced. A node that fails its wait marks only its own host failed, so the next wave still restarts its nodes. HAProxy's single active backend is node 0. NOT AVAILABLE Whether node 0's wave runs first
Blast radius DB cluster
VM impact none directly
API impact DB connection resets
Likelihood Certain if changed
Severity High
Precautions Check wsrep_cluster_size and Synced on all nodes before; take a backup (mariadb_backup); watch between waves
Evidence fact sheet B §1.2, §1.5, §1.8 items 1 and 3; roles/mariadb/handlers/main.yml:66-78, roles/mariadb/tasks/restart_services.yml:28-39; ansible 2.9.27 lib/ansible/playbook/included_file.py:51-56,92-95 (one included file per loop item), lib/ansible/plugins/strategy/__init__.py:1045-1063 (included files run one after another); :548-561 (a failure marks only that host failed), :1019-1020 (each notified host is checked on its own); no MariaDB play sets any_errors_fatal (only nova.yml:75,265)

R10 — RabbitMQ image change (upgrade)

Operation / trigger RabbitMQ image change (upgrade)
What actually happens all brokers stopped, full message-bus outage during upgrade; config change → one-by-one restart
Blast radius all RPC
VM impact NOT AVAILABLE whether nova-compute heartbeats are lost and services are reported down
API impact yes
Likelihood Certain on upgrade
Severity High
Precautions Maintenance window; watch for agent and compute services reported down
Evidence fact sheet B §2.8 items 1–2

R11 — kolla-ansible pull

Operation / trigger kolla-ansible pull
What actually happens downloads images on every host: one pull_image per enabled container mapped to the host
Blast radius registry + network
VM impact none
API impact none
Likelihood –
Severity Low (bandwidth)
Precautions Run ahead of maintenance; rate-limit with --forks; local registry mirror
Evidence roles/service-images-pull/tasks/main.yml:2-14; kolla_docker.py:599-633

R12 — Image tag change run with deploy instead of upgrade

Operation / trigger Changing openstack_tag / *_tag and running deploy instead of upgrade
What actually happens every container is recreated (fleet-wide); upgrade-specific steps (RPC pin removal, nova-status check, online migrations except Placement's, which run inside bootstrap_placement, and, with the non-default ironic_enable_rolling_upgrade: no, Ironic's inside bootstrap_ironic) do not run. Neutron: instead of the rolling expand → restart → contract (default neutron_enable_rolling_upgrade: yes), bootstrap_neutron runs neutron-db-manage … upgrade head for neutron, neutron-dynamic-routing, neutron-fwaas and neutron-vpnaas with the new image before the old neutron_server containers restart; NOT AVAILABLE whether upgrade head applies the expand and contract branches together, which would run contract migrations under live old-version servers
Blast radius fleet-wide
VM impact as R1 + R7 + R8 together
API impact yes
Likelihood Certain
Severity Critical
Precautions Use pull then upgrade (Ussuri docs); per-service tags; ANSIBLE_SERIAL
Evidence kolla_docker.py:403-418,781-803 (new image → recreate); doc/source/user/operating-kolla.rst:119-142; roles/neutron/tasks/deploy.yml:18-21, roles/neutron/tasks/bootstrap_service.yml:2-22, roles/neutron/tasks/rolling_upgrade.yml:13-93; kolla docker/neutron/neutron-server/extend_start.sh:5-12, docker/placement/placement-api/extend_start.sh:5-9, docker/ironic/ironic-api/extend_start.sh:5-8; roles/ironic/tasks/bootstrap_service.yml:16, roles/ironic/defaults/main.yml:206; Kolla images §4

R13 — Rebuilt image under the same tag, then deploy/reconfigure without pull

Operation / trigger Rebuilt image pushed under the same tag, then deploy/reconfigure without pull
What actually happens nothing changes (only absent images are pulled). After pull: recreate, plus loop-notify restarts
Blast radius – / role-wide
VM impact as R1
API impact –
Likelihood –
Severity Medium (drift)
Precautions Use immutable tags; always pull deliberately
Evidence kolla_docker.py:299-307,403-418,781-808; loop-notify (Tags §2.4)

R14 — bootstrap-servers re-run on a live host

Operation / trigger bootstrap-servers re-run on a live host
What actually happens can restart the Docker daemon (if daemon.json changes) → every container on the host restarts, on all hosts at once by default; also disables firewalld/ufw, sets SELinux permissive, removes host packages (open-iscsi, libvirt*, chrony, …)
Blast radius per host / fleet
VM impact Docker restart = nova_libvirt + OVS restart → see R1/R7
API impact yes
Likelihood Medium
Severity Critical
Precautions Run only with --limit on new hosts, or -e kolla_serial=1; diff daemon.json first
Evidence fact sheet E §1–2

R15 — kolla-ansible stop

Operation / trigger kolla-ansible stop
What actually happens stops all Kolla containers (incl. nova_libvirt, OVS, MariaDB) on targeted hosts
Blast radius targeted hosts
VM impact nova_libvirt and OVS containers stopped; NOT AVAILABLE whether VM network traffic stops (see R7)
API impact yes
Likelihood Certain
Severity Critical
Precautions Use --limit + tags + skip_stop_containers; MariaDB then needs mariadb_recovery
Evidence tools/kolla-ansible:441-453; fact sheet B §1.3 (stop), §1.8 item 4

R16 — kolla-ansible destroy

Operation / trigger kolla-ansible destroy
What actually happens removes containers, volumes, /etc/kolla/* (except a few files), all network namespaces and tap/brq/vxlan links (tools/cleanup-host)
Blast radius targeted hosts incl. deploy host (hosts: all)
VM impact total
API impact total
Likelihood Certain
Severity Critical
Precautions Never on production; there is no --limit safety net beyond what you pass
Evidence fact sheet E §6

R17 — prune-images

Operation / trigger prune-images
What actually happens removes dangling Kolla images only
Blast radius per host
VM impact none
API impact none
Likelihood Low
Severity Low
Precautions –
Evidence fact sheet E §7

R18 — mariadb_recovery

Operation / trigger mariadb_recovery
What actually happens stops every MariaDB node, even healthy ones, and bootstraps from the highest seqno
Blast radius DB cluster
VM impact none directly
API impact full DB outage
Likelihood Certain
Severity High
Precautions Only when the cluster is fully down; identify the node with the highest seqno manually first
Evidence fact sheet B §1.3 (Recovery step 3), §1.8 item 5

R19 — Keystone reconfigure

Operation / trigger Keystone reconfigure (any keystone change, including memcached/RabbitMQ membership)
What actually happens all keystone containers restart on all hosts at once; fernet keys re-pushed from the first running node, deleting others' keys; db sync runs
Blast radius identity
VM impact none
API impact NOT AVAILABLE whether authentication fails while keystone restarts
Likelihood Certain if changed
Severity Medium–High
Precautions ANSIBLE_SERIAL; verify fernet key consistency before and after
Evidence fact sheet B §3.5, §3.6, §3.7, §3.9 items 1–2

R20 — Glance reconfigure / deploy

Operation / trigger Glance reconfigure / deploy
What actually happens toggles global MariaDB log_bin_trust_function_creators 1→0 around db sync; with the file backend only glance-api[0] exists → any restart is a full Image API outage
Blast radius DB + glance
VM impact NOT AVAILABLE whether snapshots in progress fail
API impact Image API outage
Likelihood Certain
Severity Medium
Precautions Avoid during image-heavy operations
Evidence fact sheet C §1

R21 — Enabling Swift (or glance_backend_ceph) on a running cloud

Operation / trigger Enabling Swift (or glance_backend_ceph) on a running cloud
What actually happens silently switches Glance's backend; NOT AVAILABLE whether existing file-store images stay readable
Blast radius glance
VM impact NOT AVAILABLE whether boots from existing images fail
API impact yes
Likelihood High
Severity High
Precautions Set glance_backend_* explicitly before enabling Swift
Evidence fact sheet C §1.8

R22 — Inventory reordering

Operation / trigger Inventory reordering (haproxy, mariadb, glance, nova-conductor, keystone groups)
What actually happens keepalived priorities change; MariaDB restart waves and active backend move; glance moves (file backend); bootstrap/discovery target changes
Blast radius per group
VM impact indirect
API impact possible
Likelihood Medium
Severity High
Precautions Treat inventory order as configuration; never reorder casually
Evidence fact sheets A §1.8, B §1.2, §1.5, C §1

R23 — Any run with --limit on a large inventory

Operation / trigger Any run with --limit on a large inventory
What actually happens fact gathering for all hosts is executed sequentially by the limited hosts (delegated loop) → long runtime; /etc/hosts and other cross-host files are not updated on non-limited hosts
Blast radius –
VM impact none
API impact none
Likelihood Certain
Severity Low (time), Medium (drift)
Precautions Enable fact caching (ansible-tuning.rst); follow up with a full run when cross-host config changed
Evidence gather-facts.yml:29-50 (each limited host loops over its share of groups['all']: one delegated setup per host without facts); ansible 2.9.27 lib/ansible/executor/task_executor.py:317-367 (loop items run one after another)

R24 — Effective container stop timeout is 10 s

Operation / trigger Effective container stop timeout is 10 s, not docker_graceful_timeout
What actually happens on every restart, a service still running 10 s after SIGTERM is SIGKILLed (heat-engine, cinder-volume copies, glance uploads); for nova_libvirt this matters only if libvirtd has not exited by then (Nova deep dive §5). NOT AVAILABLE Whether services started by a shell wrapper that does not exec them (e.g. neutron-l3-agent, haproxy, ovs-vswitchd, ovsdb-server) receive SIGTERM at all (Kolla images §2.6)
Blast radius all restarts
VM impact in-flight operations killed
API impact –
Likelihood Certain
Severity Medium
Precautions Drain long operations before restarts; patch kolla_docker or pass graceful_timeout if needed
Evidence kolla_docker.py:871-884,892-904,991,1037-1047; group_vars/all.yml:153; Repository architecture §6; kolla docker/base/Dockerfile.j2:434, docker/base/start.sh:21

R25 — -t common believed to reconfigure fluentd/cron

Operation / trigger -t common believed to reconfigure fluentd/cron
What actually happens no-op → config drift remains and is applied unexpectedly later by an unrelated service run
Blast radius –
VM impact –
API impact –
Likelihood Certain
Severity Low–Medium (surprise)
Precautions Use -t chrony (all hosts) or a service tag; verify with docker exec … kolla_set_configs --check
Evidence roles/common/tasks/main.yml:1-10; Tags §2.1

Heat map (likelihood × severity)

quadrantChart
  title Risk heat map (relative)
  x-axis Low likelihood --> High likelihood
  y-axis Low severity --> High severity
  quadrant-1 Prevent or control strictly
  quadrant-2 Prepare contingency
  quadrant-3 Accept
  quadrant-4 Standardise procedure
  R1 nova compute change: [0.85, 0.75]
  R3 RabbitMQ membership: [0.9, 0.8]
  R5 ml2 override: [0.8, 0.7]
  R7 OVS restart: [0.6, 0.95]
  R8 HAProxy restart: [0.75, 0.65]
  R12 tag change via deploy: [0.55, 0.93]
  R14 bootstrap servers rerun: [0.4, 0.88]
  R16 destroy: [0.05, 0.98]
  R11 pull: [0.9, 0.15]
  R25 common tag noop: [0.88, 0.3]
  R24 10s stop timeout: [0.95, 0.5]

To remember

Lumo: if you keep only 5 things from this page, keep these.

  • Rated Critical: openvswitch_vswitchd restart or recreate (R7), image tag change run with deploy instead of upgrade (R12), bootstrap-servers re-run (R14), stop (R15), destroy (R16).
  • A config change touching nova-compute, then deploy/reconfigure, restarts nova_compute, nova_libvirt and nova_ssh on every affected compute, all at once with the default serial 0.
  • Whether running VMs keep running, and whether live migrations in flight fail, during that restart is NOT AVAILABLE
  • Before a nova-compute change: genconfig + diff, then deploy-containers --limit in batches; drain live migrations first; validate libvirt restart behaviour in staging.
  • Changing the image tag and running deploy instead of upgrade recreates every container fleet-wide and skips the upgrade-specific steps; use pull then upgrade (Ussuri docs).

What would you do?

Lumo: a situation you could meet on a real platform, and three ways to react. Pick the one you would choose: I will tell you what this page says about it. Nothing is recorded.

Scenario 1: A new image tag on a running cloud

You must move your production cloud to a new openstack_tag. A colleague has already changed the tag in globals.yml and proposes to run kolla-ansible deploy, "since deploy is idempotent anyway".

What would you do?

See every choice explained
  • Best choice: Run kolla-ansible pull first, then upgrade with per-service tags and ANSIBLE_SERIAL.. These are exactly the precautions for R12 (Image tag change run with deploy instead of upgrade): use pull then upgrade (Ussuri docs); per-service tags; ANSIBLE_SERIAL.
  • Avoid: Run kolla-ansible deploy with the new tag, as proposed.. This is R12, rated Critical: every container is recreated (fleet-wide), and upgrade-specific steps (RPC pin removal, nova-status check, online migrations, except Placement's) do not run. For Neutron, bootstrap_neutron runs neutron-db-manage … upgrade head with the new image before the old neutron_server containers restart.
  • Works, but risky: Run kolla-ansible upgrade on the whole cloud at once, with no tag and no serial, and let each host fetch its images.. upgrade is the right action, but this skips the precautions the register gives for R12: use pull then upgrade, per-service tags, ANSIBLE_SERIAL.

Read the section.

Scenario 2: Re-running bootstrap-servers for a new compute

You are adding one compute to a cloud with 40 live computes. To prepare the new host, a colleague wants to run kolla-ansible bootstrap-servers against the whole inventory, "to keep every host consistent".

What would you do?

See every choice explained
  • Avoid: Run bootstrap-servers on the whole inventory, as suggested.. This is R14, rated Critical: it can restart the Docker daemon (if daemon.json changes), and then every container on the host restarts, on all hosts at once by default.
  • Works, but risky: Run bootstrap-servers on every host with -e kolla_serial=1.. Serial is one of the R14 precautions, but the live hosts are still re-bootstrapped: the run can restart the Docker daemon if daemon.json changes, disables firewalld/ufw, sets SELinux permissive and removes host packages (open-iscsi, libvirt*, chrony, …).
  • Best choice: Diff daemon.json first, then run bootstrap-servers --limit on the new host only.. The precautions for R14 are: run only with --limit on new hosts, or -e kolla_serial=1; diff daemon.json first.

Read the section.

Check yourself

Lumo: 3 quick questions to check the main ideas of this page. Choose an answer to see the explanation and the section that gives the evidence. Your score counts your first choices and stays in this browser only.

1. Which of these operations is rated Critical?
Show the answer

Answer: kolla-ansible stop (R15). The risks rated Critical are R7, R12, R14, R15 and R16. Read the section.

2. A nova-compute config change is applied by reconfigure with the default serial 0. What restarts?
Show the answer

Answer: nova_compute, nova_libvirt and nova_ssh on every affected compute, all at once. This is risk R1. Read the section.

3. Is it known whether running VMs keep running during that restart?
Show the answer

Answer: No: the sources do not establish it. Whether live migrations in flight fail and whether running VMs keep running are NOT AVAILABLE (R1). Read the section.